Tom Lee Park - Cutbank Bluff Finishes
Phase 2 - Finishes Package
Status
Pending
Company & Contacts
Memphis River Parks Partnership
Art Davis
(901) 312-9190
Location
Riverside Drive, TN 38103
MWBE Workshop will be held on 2/16/2021 at 2:00 PM. Meeting information is below:
Please join my meeting from your computer, tablet or smartphone.
Go To Meeting
You can also dial in using your phone.
United States (Toll Free): 1 877 309 2073
United States: +1 (571) 317-3129
Plans noted as Volume 1 Conformed Set dated 12/18/2020 are provided for information and coordination only. This work is underway.
Subgrade for the switchback pathway will be CTB that is left 1” low (6” below the finish grade)
Subgrade provided under Phase 1 for the horticultural soils shall be as follows:- All areas beginning at the existing Railroad and going down the bluff will be graded under Phase 1 to finish grade minus 6” (T-SP, SP-SS, L-SP, S-SP and upper T-SP).
- The 2 T-SP areas just East of Riverside Drive will be graded under Phase 1 to finish grade minus 1’-4”.
- Benching and excavation for the required horticultural soil depth shall be included in your bid for the Phase 2 work.
Electric work under Phase 1 includes rough-in of conduit, wiring and the install of the
fixtures. Fixtures are to be provided under Phase 2.